01 — DefinitionWhat is on-site refractory supervision?
On-site refractory supervision is the independent technical oversight of a refractory lining project, from demolition of the old refractories to commissioning of the new ones. The supervisor checks the compliance of the installation, adherence to procedures and quality at every stage.
It is the assurance that the refractory investment — materials + labour + production shutdown — delivers the expected service life. A poor installation can halve the service life of a refractory that was otherwise perfectly specified.
Why installation quality is decisive
A poorly installed refractory — incorrect joints, faulty anchors, unsuitable drying, tolerances not met — degrades prematurely, whatever its intrinsic quality. Installation is often the number one factor in actual service life. Supervising it means protecting the entire investment.
Supervision independent of the installers
Our independence from the installation contractors guarantees objective oversight. We are neither judge nor party: our only interest is that your installation is compliant and durable. We supervise throughout Europe and internationally, including on complex projects abroad.
02 — MethodHow do you supervise the installation?
Supervision in four steps, from site preparation to commissioning. A continuous on-site presence and quality control at every critical phase.
-
Site preparation (materials, teams, schedule)Step 1
Upfront verification: compliance of the delivered materials, qualification of the installation teams, approval of the schedule and procedures. Nothing starts without validated preparation.
-
Supervision of the demolitionStep 2
Oversight of the demolition of the old refractories: safety, preservation of structures, surface preparation for the new installation.
-
Supervision of the installation of the new refractoriesStep 3
Continuous monitoring of the installation: joints, anchors, geometric tolerances, adherence to manufacturer procedures. Immediate correction of deviations.
-
Quality control and commissioningStep 4
Final quality control, supervision of drying and heat-up (the critical heating curve), approval of commissioning.